Difference between revisions of "Step Complete"
From SAM Docs
(→Step Complete and Inspector Confirmation) |
|||
Line 6: | Line 6: | ||
[[File:Stepcomp2.PNG]]<br><br> | [[File:Stepcomp2.PNG]]<br><br> | ||
Once each step is confirmed by the Inspector, a set percentage of the inspection report total surface area is entered into the Step Complete Report. <br> | Once each step is confirmed by the Inspector, a set percentage of the inspection report total surface area is entered into the Step Complete Report. <br> | ||
− | eg if the Inspection Report total surface area is 10square metres and the pre ctreatment step is confirmed as complete by the inspector then 10% of the surface area is calculated for the days progress | + | eg if the Inspection Report total surface area is 10square metres and the pre ctreatment step is confirmed as complete by the inspector then 10% of the <br> |
+ | surface area is calculated for the days progress<br> | ||
Additionally anything that is 'Inspector confirmed' on a given day is reported in the daily report <br> | Additionally anything that is 'Inspector confirmed' on a given day is reported in the daily report <br> |
Revision as of 11:08, 20 April 2017
Step Complete and Inspector Confirmation
The Step complete and Inspector Confirmation tick boxes allow monitoring and reporting of progress
Step Complete confirmation is normally selected by the Contractor; this advises the Client Inspector that the step is ready for inspection
Once each step is confirmed by the Inspector, a set percentage of the inspection report total surface area is entered into the Step Complete Report.
eg if the Inspection Report total surface area is 10square metres and the pre ctreatment step is confirmed as complete by the inspector then 10% of the
surface area is calculated for the days progress
Additionally anything that is 'Inspector confirmed' on a given day is reported in the daily report