Difference between revisions of "Step Complete"

From SAM Docs
Jump to: navigation, search
(Step Complete and Inspector Confirmation)
Line 8: Line 8:
 
eg if the Inspection Report total surface area is 10square metres and the pre ctreatment step is confirmed as complete by the inspector then 10% of the <br>
 
eg if the Inspection Report total surface area is 10square metres and the pre ctreatment step is confirmed as complete by the inspector then 10% of the <br>
 
surface area is calculated for the days progress<br>
 
surface area is calculated for the days progress<br>
 +
Percentages for each stage are predetermined as the table below but can be adjusted to suit each Client individually
 +
 
Additionally anything that is 'Inspector confirmed' on a given day is reported in the daily report <br>
 
Additionally anything that is 'Inspector confirmed' on a given day is reported in the daily report <br>

Revision as of 11:15, 20 April 2017

Step Complete and Inspector Confirmation

The Step complete and Inspector Confirmation tick boxes allow monitoring and reporting of progress

Stepcomp1a.png
Step Complete confirmation is normally selected by the Contractor; this advises the Client Inspector that the step is ready for inspection
Stepcomp2.PNG

Once each step is confirmed by the Inspector, a set percentage of the inspection report total surface area is entered into the Step Complete Report.
eg if the Inspection Report total surface area is 10square metres and the pre ctreatment step is confirmed as complete by the inspector then 10% of the
surface area is calculated for the days progress
Percentages for each stage are predetermined as the table below but can be adjusted to suit each Client individually

Additionally anything that is 'Inspector confirmed' on a given day is reported in the daily report